LOT 1

Rehabilitation and extension Geed Deeble well field – FUNDED BY EU IMPLEMENTED BY UN-HABITAT under HUWSUP project  – to be completed 2016, designed by Fichtner.

LOT 2

Replacement of Pipeline System From Geed Deeble to Storage
Facilities. FUNDED BY EU IMPLEMENTED BY UN-HABITAT – to be completed 2016, designed by Fichtner.

LOT 4

Construction of Infiltration Gallery in Haraf. –COMPLETED 2014 with 25% OF HWA OWN FUNDS.

LOT 5

Drilling and Installation of Productive Bore Holes at Hora Haadley. – FUNDED UNDER SDF PHASE 1 – 2014.

LOT 6

Construction and equipment of Hora Haadley Well field and Transmission . – FUNDED UNDER SDF PHASE 1 – 2014

LOT 3

Rehabilitation and Extension of the Urban Distribution System. – NOT FUNDED – Euro 10 – 15m.